How to Write a Change Request Process for Extra Client Work

Download Hemory
On this page

A client asks for one more deliverable, then another. If the proposal does not say what is included or how added work will be handled, even a small request can quietly change the scope. A clear out-of-scope section and change-request process give both sides a chance to discuss cost and timing before the work begins.

TL;DR

  • Define the included deliverables and limits first; exclusions only make sense against that baseline.
  • Treat candidate exclusions as items to confirm against the proposal and client discussions, not as agreements already reached.
  • Review each new request for scope, price, and timeline impact, then get written approval before starting the added work.

Start with the agreed scope

Before listing exclusions, state what the client is buying: deliverables, quantities, revision rounds, dependencies, and any relevant dates. Use the proposal or statement of work (SOW) as the baseline, and compare it with what was discussed and accepted.

A request mentioned in a conversation is not automatically included or excluded. Distinguish among an idea, an open request, an agreed deliverable, and a later change. If the records do not show whether an item was accepted, leave its status open and ask for confirmation rather than writing it into the SOW as settled.

Draft an out-of-scope section

Use the following structure as a starting point. Replace the bracketed details, remove anything that does not fit the project, and confirm each item before including it.

Out of scope: Unless expressly listed in the included scope, this engagement does not include:

  • Additional deliverables beyond [the named deliverables and quantities].
  • Additional revision rounds beyond [the number of included rounds] or revisions requested after [the agreed approval point].
  • Content or versions for additional [languages, audiences, or channels] not listed in the scope.
  • [Implementation, integration, or deployment work] beyond the agreed [design, advisory, or delivery work].
  • Ongoing support, maintenance, or optimization after [the defined handoff or end of the engagement].

Requests for work outside the included scope will be reviewed through the change-request process before work begins.

These are candidate exclusions, not a checklist to copy wholesale. For example, if implementation is part of the project, do not exclude it. If the proposal does not limit revision rounds, do not add a limit without confirming it with the client.

Use discussions to confirm the candidates

The relevant information may be in the SOW, a project document, a CRM, meeting notes, or recorded conversations. Start with the sources your team already uses. If the client discussions were captured in Hemory and are accessible there, its built-in Q&A can help retrieve details across conversations. For example, ask which additional deliverables or constraints were discussed for the project, and whether the available conversation context indicates they were agreed or remain open. Hemory can help surface relevant recorded context; it cannot recover an uncaptured exchange or guarantee that every relevant conversation will appear. Check consequential details against the source material and current project documents. (Hemory Features)

For each candidate, record what supports it and its current status before drafting the SOW:

Candidate itemWhat to establishDrafting treatment
Additional deliverableWas it requested, included, or left open?Include only if the baseline excludes it; clarify any unresolved status.
More revisionsWhat number or approval limit was actually specified?State a limit only if it is agreed and relevant to the project.
New audience or formatDoes the scope name the audience, language, channel, or format?Define the included versions; list only genuinely excluded ones.
Implementation or supportDoes the engagement include delivery, setup, or work after handoff?Describe the boundary in terms of the actual services and end point.

A short review note can help: Included, excluded, proposed, or unclear. Do not treat a client’s suggestion as an accepted decision, or a mention by a team member as authority to commit the project.

Set a simple change-request process

A process can be short and still make the next steps clear:

  1. Record the request. Capture what the client wants changed or added and any deadline or constraint they supplied.
  2. Compare it with the scope. Identify the relevant included deliverable or exclusion. If the documents and discussions do not settle the status, ask a focused question.
  3. Assess the impact. Ask the people responsible for delivery to estimate any change to fees, schedule, deliverables, or dependencies. Do not invent figures when the impact has not been assessed.
  4. Send the proposed change in writing. Describe the requested work, any price or timeline adjustment, and what remains unchanged. Mark estimates or unresolved points clearly.
  5. Wait for approval before starting. Begin the additional work only after the appropriate parties have approved the revised scope and any applicable price or schedule changes in writing.

The process does not mean every request must cost more or delay delivery. It means the impact is discussed and agreed before the team takes on work that changes the baseline.

Copy-ready change-request wording

If you request work that is not included in the scope above, we will review the request and send you a written summary of the proposed work, any impact on fees, and any impact on the timeline. We will begin the additional work only after you have approved the revised scope and applicable changes in writing. Until then, the request remains open and is not treated as an approved change.

Adapt the approval route and terminology to your organization and contract. This is drafting guidance, not legal advice; have the final terms reviewed as appropriate for your situation.

Example: apply the wording to a defined project

Consider a proposal that includes one English-language landing page and two revision rounds, with no implementation work. Those scope details establish the baseline for this example; they are not assumptions to apply to another project.

If the client later asks for a Spanish version, compare the request with the stated deliverables. The SOW could list these candidate exclusions, after confirming they match the discussions and are not already included:

  • Additional language versions beyond the specified English page.
  • Additional revision rounds beyond the two included rounds.
  • CMS implementation, because the example scope covers the page deliverable but not implementation.
  • Ongoing content updates or optimization after handoff, if those services are not included elsewhere in the proposal.

The Spanish version is a request to assess, not an approved change. The team would estimate its scope and any price or schedule impact, send the proposal for review, and wait for written approval before starting it. If the client had already accepted the Spanish version as part of the original scope, it would not belong on the exclusion list.

FAQ

Does every extra client request need to be charged separately?

No. The process calls for reviewing the request and discussing any price or timeline impact. The parties can decide that the work fits the existing scope, has no additional fee, or needs a revised agreement. Record the decision before proceeding.

Should an item be excluded just because it came up in a conversation?

No. Check whether it was only suggested, left open, or accepted as part of the work. Use the proposal and available discussion records together, and ask for clarification when the status is unresolved.

Before sending the proposal

Confirm the included work, remove exclusions that conflict with it, and leave unresolved items open rather than presenting them as agreed. A concise change process can then make each new request a clear discussion about scope, price, and timing before additional work starts.

Start building your memory palace

Download Hemory — from today on, every real conversation becomes material you can generate from tomorrow.

Get Hemory for iOS Get Hemory for Android Download APK

macOS, Windows, Linux, Web, and Self-host coming soon