# How to Update a RAID Log Without Inventing Changes

> Use a clear process to update a RAID log from weekly discussions. Separate proposals from confirmed changes, verify owners and dates, and keep unresolved items open.

- URL: https://www.hemory.com/blog/workflows/raid-log-change-process/
- Language: English (en)
- Author: Hemory Team
- Published: 2026-11-28
- Last updated: 2026-11-28
- Summary: Update a RAID log by comparing each discussed change with the current entry, recording what the evidence actually supports, and leaving uncertain owners, dates, or status changes unresolved. A simple review process helps distinguish proposals from accepted decisions and commitments. Hemory can help retrieve context from discussions captured there; you review the evidence and make approved changes in your project log.
- Tags: RAID log, project management, meeting follow-up, decision tracking

[A week of project discussions](/blog/searchable-memory/weekly-conversation-review/) can produce several possible changes to a RAID log. The difficult part is deciding what the conversations actually confirmed. A suggestion is not automatically a decision, a person mentioned in discussion is not necessarily an owner, and a missing date should not be filled in from guesswork.

Use the process below to review each change, preserve what is known, and leave anything unresolved visible. If relevant discussions were captured and are accessible in Hemory, [its Q&A](/features/) can help retrieve context; you remain responsible for checking the result and approving edits to your project log.

## TL;DR

- Compare each possible change with the current RAID entry before editing it.
- Record a proposal as proposed; change an item to confirmed, assigned, or closed only when the evidence supports that status.
- Keep unsupported owners, dates, decisions, and closure details marked as unresolved or unstated.
- Use Hemory to retrieve context from discussions captured there, then review and apply approved changes in your usual project log.

## What counts as a confirmed RAID log change?

A RAID log tracks risks, assumptions, issues, and dependencies. Teams may use different fields and status labels, so follow your organization’s definitions. The key is to distinguish what was raised from what was accepted or has actually changed.

Use the evidence in the discussion and current project records to classify each update:

| Evidence in the source | How to treat it |
|---|---|
| Someone raises a concern or suggests a response | Record it as a proposed change or an item for review. Do not present it as an accepted decision. |
| The relevant decision-maker or team accepts a change | Update the affected entry to reflect the decision and preserve any stated conditions. |
| A person is asked to take an action and accepts, or the assignment is otherwise clearly confirmed | Record that person as the owner. A name mentioned in the conversation alone is not enough. |
| A date is explicitly agreed or supplied by a current authoritative project record | Enter that date. If no date is stated, leave it unstated rather than estimating one. |
| Evidence shows the issue is resolved or the risk or dependency no longer applies | Close or revise the entry according to your team’s status rules. Discussion of a possible resolution is not proof that it happened. |

[A commitment can be real](/blog/searchable-memory/decisions-commitments-and-ideas/) even when it has no deadline. Preserve the commitment and leave the date blank or mark it “Not stated,” according to your log’s conventions. For a conditional decision or commitment, record the condition as well as the accepted action. Do not treat a condition as fulfilled until there is evidence that it has been met.

## A step-by-step process for weekly updates

### 1. Start with the current log

Review the existing RAID entries before adding new ones. Note each item’s identifier, category, description, status, owner, date, and any conditions or linked actions your team tracks.

This helps you distinguish a genuinely new item from a follow-up, a proposed change to an existing item, or a repeated mention of something already recorded. Similar wording or the same people appearing in two discussions does not, by itself, establish that the items have the same scope.

### 2. Gather relevant discussion and project evidence

Use the sources available for the project: the current log, meeting notes, decisions, project documents, and relevant conversations. If you use Hemory, the discussion must have been captured there and be accessible to you. Its built-in Q&A supports questions about your Memory, including multi-turn transcript-based questions and retrieval across conversation sessions. Treat retrieved material as context to review, not proof that every discussion from the week was captured or found.

For example, ask a focused question such as: “What was discussed about the staging access dependency, including any decision, assigned owner, date, or condition?” Review the answer against the relevant source material and current project information. If the necessary detail has no usable record, leave it unresolved or [ask someone who can confirm it](/blog/searchable-memory/clarify-a-past-conversation/).

![Agent session searching a past sync and drafting a follow-up checklist.](/blog-assets/article-images/hemory-memory-qa-agent.webp)

*Retrieve past commitments and draft follow-up tasks.*

A transcript records speech; it does not guarantee that the transcription is complete or that a statement became an accepted decision. A summary, project record, or later update may also contain important detail. Compare sources for scope, date, acceptance, and current status instead of assuming one format is always authoritative.

### 3. Classify each change before editing

For every candidate update, decide whether it is:

- **New:** A RAID item not already represented in the log.
- **A proposed change:** Someone suggested changing the description, response, owner, date, or status, but acceptance is not established.
- **A confirmed change:** The relevant decision or assignment is supported by the available evidence.
- **A progress update:** Work has advanced, but the item remains open.
- **Ready for closure or removal:** Evidence supports that the issue is resolved or the risk or dependency no longer applies, under your team’s rules.
- **Unresolved:** The source is incomplete, ambiguous, or inconsistent, or required confirmation is still missing.

Do not turn “we could move the test to staging” into a confirmed plan. Do not change an owner because someone offered to look into an item unless the assignment was accepted or otherwise confirmed. Keep the distinction in the entry itself so another reader can see what still needs a decision.

### 4. Update only the fields the evidence supports

Change the description, owner, date, status, impact, mitigation, or other fields only when the source supports that specific change. A confirmed update to one field does not establish the others. For instance, an accepted action may have an owner but no agreed due date.

Preserve any established part of an entry when another part remains uncertain. If a decision is confirmed but its effective date is not, update the decision and leave the date open. If a proposed owner has not accepted the work, record the assignment as needing confirmation instead of presenting that person as accountable.

Use your team’s existing status labels. If the log has no suitable label for a proposal, use a clear note such as “Proposed—pending confirmation” rather than silently treating it as approved.

### 5. Check for conflicts and dependencies

Before saving, compare the proposed edit with the current entry and other relevant project information. Look for changed assumptions, conditions, owners, dates, or dependencies. A later mention does not automatically replace an earlier agreement; establish whether the team accepted a change and which parts it affects.

If sources conflict, preserve the discrepancy and identify the specific point that needs confirmation. Do not resolve it by choosing the newer-sounding statement or by combining incompatible details into a single confident entry.

### 6. Apply the approved changes and retain an audit trail

Make the approved edits in your usual RAID log or project system. Hemory can help retrieve discussion context, but retrieval does not itself confirm a change or update your external project log. Record the change date, supporting source, and any remaining question if your team’s process allows it. This helps the next reviewer understand what changed and why.

## Example: a possible staging change

Suppose a discussion includes these points: the team may move an API test to staging after an access review, and Priya can investigate the access question. No one confirms the staging change, Priya does not accept ownership, and no date is stated.

A cautious update might look like this:

| Field | Entry |
|---|---|
| RAID type | Dependency or issue, based on the existing log’s definitions |
| Change | Proposed: consider moving the API test to staging after the access review |
| Status | Proposed—pending confirmation, if this fits the team’s status conventions |
| Owner | Unconfirmed; Priya’s role needs confirmation |
| Due date | Not stated |
| Next step | Confirm whether the staging change is accepted and who owns the access review |

This entry preserves the proposal without turning it into an approved plan. If the team later accepts the change, update that decision. Add an owner or date only when those details are confirmed. Close the dependency only when evidence supports closure under the project’s rules.

## A final review before you save

For each edited item, ask:

- Does the source support this specific change, rather than merely mention it?
- Is a proposal clearly distinguished from an accepted decision or commitment?
- Has the named owner actually been assigned or confirmed?
- Is the date explicit, or have I accidentally inferred one?
- Does the status reflect current evidence, including any conditions that remain open?
- If the evidence is incomplete or conflicts with another source, is that uncertainty visible?

If an answer reveals a gap, leave the relevant field unchanged or mark it for confirmation. A complete-looking log is less useful than an accurate one.

## FAQ

### Should I create a new RAID item for every change mentioned in a meeting?

No. First compare the discussion with existing entries. Add a new item only when it represents a distinct risk, assumption, issue, or dependency under your team’s definitions. A follow-up or repeated mention may belong in an existing entry.

### Can I mark an item resolved because someone said it should be fixed soon?

No. A plan or expectation is not evidence of resolution. Keep the item open until you have evidence that the issue is resolved or the risk or dependency no longer applies.

### What if the discussion supports an owner but not a due date?

Record the owner only if the assignment is confirmed. Leave the due date unstated or mark it according to your log’s convention, and follow up if a date is needed.

### Does Hemory update my RAID log after retrieving a discussion?

This process uses Hemory to retrieve context from conversations captured there. Review the result and apply approved changes in your usual project log; do not assume retrieval updates an external system.

## Next step

Choose one RAID entry that may have changed this week. Compare it with the relevant discussion and current project information, classify each possible edit, and update only the fields the evidence supports. If you use Hemory, retrieved context can reduce the need to reconstruct the discussion from memory; your review keeps proposals, commitments, and current status distinct.